Asset Management
LibertyStream has signed a feedstock agreement with Goodnight Midstream to support its first commercial lithium carbonate facility in North Dakota's Bakken, advancing plans to extract battery-grade lithium from produced water.
The loan to Arena Energy will generate an estimated 38,600 B/D in new production from 22 platforms in the Gulf.
This article from Murphy Oil outlines a modernization effort that resulted in increased scenario simulation capacity by five to 10 times.
-
The authors of this paper present the results of an assessment of two regions in Uruguay suitable for bottom-fixed offshore wind technologies.
-
The discovery in Putumayo could benefit from nearby existing infrastructure.
-
The Anita Garibaldi was built by MODEC and will produce Marlim and Voador together with FPSO Anna Nery, already in operation.
-
Mukuyu-1 sidetrack proves a working hydrocarbon system in the Cabora Bassa basin.
-
Wellesley estimates that the drilling campaign has proved a developable gas-condensate accumulation of 60 to 100 million BOE.
-
The Uganda oil project envisions drilling more than 450 wells on 35 well pads, leading to an estimated production of 230,000 BOPD at its peak once production starts up.
-
The next phase of drilling is expected to resume in mid-2024 and includes several sidetrack wells, long-reach directional wells, and stratigraphic exploration wells.
-
Challenges to development, including costs, cited as reasons for turning back the acreage.
-
Jackup rig Borr Norve has started drilling operations on the project’s fourth production well, DHIBM-6H.
-
Fervo Energy’s bet that fracturing methods can be used for geothermal power is looking like a winner.