Eagle LNG Receives FERC Approval for Jacksonville Facility

The small-scale facility in northern Florida will support the export of LNG to markets that cannot be served by large LNG carriers, including a number of ports in Caribbean nations. Up to 100 LNG carriers are expected to run through the Jacksonville LNG export terminal each year.

ogf-2019-09-jacksonville-lng-approval.jpg
Eagle LNG Partners

The US Federal Energy Regulatory Commission (FERC) has authorized Eagle LNG to site, construct, and operate a proposed facility located on the St. Johns River in Jacksonville, Florida. The export facility and terminal will have a production capacity of approximately 1.65 million LNG-gal/D, with 12 million LNG-gal of storage plus onsite marine and truck loading capabilities.

Eagle LNG said the Jacksonville LNG project will cost around $500 million to build. It will be located between the Marathon Petroleum marine terminal and the US Navy fuel pier, just north of the St. Johns River Federal Channel. Berthing and mooring facilities will ensure the accommodation of LNG vessels.

The facility will have three trains, each with a production capacity of 44 MMcf/D of domestically produced natural gas. A 45,000-cbm LNG storage tank will be constructed, as well as a marine load-out facility and a dock designed to hand small and mid-sized LNG vessels and bunkering barges. The total project capacity will be around 0.33 mtpa.

The Jacksonville facility will receive natural gas from Peoples Gas System, liquefy it, and store and transfer the LNG onto carriers for export to foreign markets. The small-scale project will help support the export of LNG to markets that cannot be served by large LNG carriers, such as small ports in the Caribbean Sea. In its FERC filing, the company estimated that approximately 40 to 100 LNG carriers will come through the terminal each year once it is operating at full production capacity.

Eagle LNG already operates a small-scale natural gas liquefaction plant in Maxville, approximately 24 mi west of downtown Jacksonville. It is building a fuel depot dockside on the St. Johns River to support fueling ships. Eagle LNG president Sean Lalani said in a statement that Maxville’s successful startup will serve as a template for the Jacksonville LNG facility.

“Exports in small volumes from our existing Maxville LNG facility are already providing low cost, domestically produced natural gas as an early, stable fuel source for the Caribbean,” Lalani said. “The proposed Jacksonville LNG export facility is crucial for the expansion of new US-Caribbean LNG trade opportunities.”