commissioning
-
With events such as the BP Macondo blowout in the US Gulf of Mexico (2010) and the Pemex Ayatsil-C platform accident (June), the safety risks inherent in oil and gas projects are evident.
-
Although the commissioning of a floating production system (FPS) generally takes place between the “mechanical completion” and “first oil” stages, commissioning activities begin long before then.
-
LLOG Exploration’s Delta House floating production system (FPS) looms large over Kiewit Offshore Services’ fabrication yard in Ingleside, Texas.
-
The ultimate success of a deepwater project depends on phases from early concept selection, design, construction, commissioning, and startup to operation. However, the boundaries and transfer of responsibilities may not be sharply demarcated between phases.