UK Shale Flow Test Positive, But No Regulatory Relief in Sight

UK’s first horizontal shale well has yielded positive results after an initial flow test. But further testing—and fracturing of a second well—will have to come amid a continuation of UK’s stringent regulations on induced seismicity.

jpt-2019-2-cuadrilla-shale-well-flow-test-hero.png
Cuadrilla said it shut in the well and will monitor buildup. Source: Cuadrilla.

Partial flow testing of UK’s first horizontal shale well has confirmed “a rich reservoir of recoverable high-quality natural gas,” operator Cuadrilla Resources said 6 February.

But the UK government’s 7 February refusal to relax its seismic limits during hydraulic fracturing means operations will continue to be hampered as Cuadrilla attempts to test both of its wells targeting the Bowland Shale.  

Fracturing of the first well began in October at Preston New Road in Lancashire. The Bamber Bridge-based firm shortly thereafter reported that gas had started flowing to the surface. The well, which is the first to be fractured in the UK since 2011, was drilled to more than 7,500 ft.

Francis Egan, Cuadrilla chief executive officer, said the operator “confirmed that the Bowland Shale formation fractures in a way that, from US experience, is typical of an excellent shale gas reservoir. A complex fracture network was generated in the shale and sand injected into the fractures has stayed in place during flow back.”

cuadrilla-bowland-chart.png
Regulatory hurdles removed, Cuadrilla says the Bowland Shale is “ideal for commercialization.” Source: Cuadrilla.

 

However, because of the UK Oil and Gas Authority’s mandate that Cuadrilla pause fracturing when microseismic events of 0.5 magnitude or higher are recorded near the site, just two of 41 stages have been fractured “fully as designed” and 14% of planned sand injection has taken place, Egan said. Cuadrilla has paused fracturing on several occasions.

Despite the constraints, gas flowed at a peak rate of more than 200,000 scf/D and stable rate of 100,000 scf/D. With all stages fractured, and compared with “a typical North American 2.5-km-long producing horizontal shale gas well,” Cuadrilla estimates a potential initial flow rate of 3–8 million scf/D.

Under the OGA’s traffic light monitoring system, when microseismic events hit the 0.5 magnitude threshold, the operator must stop injection for at least 18 hours, reduce pressure, and observe seismicity. The UK government has rejected calls by Cuadrilla and fellow UK shale explorer Ineos for a review of the policy.

“We set these regulations in consultation with industry, and we have no plans to review them,” said a spokesperson for the UK Department for Business, Energy and Industrial Strategy.

Cuadrilla said its plans to complete fracturing of the well and proceed with the second well were subject to the review's outcome.